In February 2023, by order of the POLIPLASTIC Group, three pneumatic hangars with a useful area of 300 m2 were manufactured and installed. The hangars are designed for laying polymer oil pipelines at the fields of Gazprom Zapolyarye LLC in Eastern Siberia. Due to the fact that construction at the sites is carried out in the Far North at temperatures below 50C, for the implementation of this project it was decided to use mobile inflatable hangars for pre-heating polypropylene pipes, followed by unwinding and laying in a trench. For the first time, a system of fastening to concrete blocks UBP-07, used by the Customer in the construction of pipelines, was introduced in pneumatic hangars. The prefabricated hangars were equipped with 7x4.5m cargo doors, technological hatches for the passage of an oil pipeline, heating systems to maintain a temperature of +15 ... +20C, as well as ventilation and lighting systems.